Guavio Hydroelectric Project - Operations Communications
Scope summary of works performed by INGETEC:
Design, tender documents preparation, bid evaluation, revision of detail
shop drawings, supervision during shop testing, erection, installation,
start-up and commissioning.
Systems and communications services:
Communication via fiber optics, data and telephone networks.
Detailed scope of works performed by INGETEC:
Fiber optics cable design (Composite cable of fiber optics + guard cable
though 230 kV power transmission line) and voice and data terminal equipment.
Communication types:
- Composite
fiber optics (guard cable + fiber optics through the Guavio - Bogota
230 kV power transmission line (90 km).
- Data
network for fiber optics supervision and digital control systems.
- Facilities
telephone networks.
Client:
Empresa de Energía Eléctrica de Bogotá - EEEB E.S.P.
(Bogota Electric Power Company)
Location:
Mámbita, Administrative Department of Cundinamarca - Colombia.
|
|