Salvajina


Concrete face gravel and rockfill dam, 148 m high, and 400 m long crest. In order to undertake construction of the dam, an upstream low-permeability core cofferdam and two 800-m long tunnels to divert the river were constructed.

The reservoir is 26 km long, has a total capacity of 906 Mm³, and floods an area of 2.031 hectares.

The project has two circular cross-section diversion tunnels that are concrete-lined between the intake structure and the valve chamber, changing to a horseshoe cross-section with a flat concrete invert between the valve chamber and the downstream portals. Tunnel diameters are 7.6 m and 8.4 m, respectively, and have a combined length of 1.583 m.

The power plant houses three vertical-axis Francis units, with a total capacity of 270 MW; included are three 4.0 m in diameter butterfly valves, three synchronous-type generators, with a capacity of 100 MVA and three three-phase power transformers.

Transmission lines are 230 kV, double circuit-type, 72 km long.

Services rendered:


Consulting services for the detail design and supervision during construction of the civil works and the erection of electromechanical equipment.

Client:

Corporación Autónoma de Valle del Cauca - CVC (Cauca Valley Authority).

Location:


Valle del Cauca, Colombia

Hydropower Projects

Transmission Lines and
Substations

Thermal Power Plants
Water and Wastewater Systems
Industrial Development
Roads and Highways
Transportation
Telecommunications
Oil Industry
Mining
Land Reclamation
Rural Development
Environmental Studies 
Claims, Disputes and Arbitrations


Home  |  Company  |  Service  |  Experience  |  Brochures  |  Site Map  |  Spanish   |   Contact



Copyright© 2004, Ingetec S.A. All rights reserved.
www.ingetec.com.co