Aguablanca


Enlargement of the Puerto Mallarino
Water Treatment Plant:

The enlargement works at the plant increased the yield of potable water from 3.3 m³/sec to 4.95 m³/sec. Such increase implied the supply and installation of a 66” diameter metal pipe between the valve chamber at the intake structure and the flow distribution chamber reactors C and D filters.

The works also involved the first phase of filter installation, two treated-water pumps, a flow distribution chamber, construction of the solids contact reactor and erection of mechanical equipment.

Construction of the Puerto Mallarino storm water pumping station, supply and equipment erection, start-up and commissioning:

The design flow was 20 m³/sec for the pumping station. The pumping station works consisted mainly of the construction of a pressure chamber, supply and erection of five pumps, the electric power substation and ancillary equipment.

Construction of the water pipe distribution network of Terrón Colorado, Sector I:

The potable water pipe distribution network has a total length of
3,500 m and the wastewater concrete pipe collection network is
7,900 m long.

Construction of the Terrón Colorado, Sector II water pipe network:

The potable water distribution network is 11,000 m long and the wastewater collection network is 11,500 m long, composed of 3,300 m of cast-iron pipes and 8,200 m of concrete pipes.

Construction of Mojica II Quarter wastewater network:

The area of influence is 23,8 ha. In addition to sewerage works (household sinks, chambers, etc) supply and installation of 12,000 m of concrete pipes was carried out with diameters varying between 8" and 30" as well as 16,300 m of 6" diameter pipes.

Services rendered:

The joint venture INGETEC S.A. - INCOL LTDA. undertook the technical and administrative supervision of five construction contracts for the Aguablanca District in the City of Cali.

Client:

EMCALI

Location:

Cali, Administrative Department of Valle del Cauca.

Hydropower Projects

Transmission Lines and
Substations

Thermal Power Plants
Water and Wastewater Systems
Industrial Development
Roads and Highways
Transportation
Telecommunications
Oil Industry
Mining
Land Reclamation
Rural Development
Environmental Studies 
Claims, Disputes and Arbitrations


Home  |  Company  |  Service  |  Experience  |  Brochures  |  Site Map  |  Spanish   |   Contact



Copyright© 2004, Ingetec S.A. All rights reserved.
www.ingetec.com.co