Representative Projects
-
Termoyopal
- La
Sierra
- Termocentro
- Martín
del Corral
|
Thermal
Power Plants
INGETEC S.A. has participated in more than twelve thermal power projects,
with a total installed capacity of 1 000 MW, of which 500 MW are currently
in operation.
The most recently completed projects are Project Management for Construction
of Termoyopal Stage 1, two 50 MW gas-operated units, and construction
of the natural gas-operated La Sierra Thermal Power Plant, including
two 150 MW open-cycle units.
INGETEC carried out the engineering supervision tasks during enlargement
of the combined-cycle Termocentro Thermal Power Plant, with a 100 MW
vapor turbine, yielding a total generation capacity of 300 MW.
Services:
- Types
of Plants:
- Coal
- Fuel oil
- Gas
- Diesel
- Combined cycle
- General
layout
- Auxiliary
systems
- Supply
and Transportation of fuel
- Cooling
Systems
- Ventilation
and air-conditioning
- Treatment
and gas-conditioning systems
- Pipes
- Waste
Disposal
- Storage
Tanks
- Structural
Design
- Electric
Power Substations and Switchyards
- Instrumentation
Systems, Control and Protections - SCADA
- Environmental
Engineering
- Quality
Assurance
- Start-up
and Commissioning
|
|