INGETEC S.A. was responsible for the planning and design of the Chingaza Water Supply System for Colombia’s capital, Bogota D.C., a city with over 6 million people, and an average fresh water demand of 27 m³/sec. Chingaza includes a 120-m high concrete face gravel fill dam impounding 223 Mm3 in the Chuza Reservoir, a 40-km long conveyance system of tunnels and pipes, and the 75 Mm³ San Rafael back-up reservoir, providing together 65% of the city’s water demand.

Recently, INGETEC carried out the feasibility and detail design for the 3,3 m³/sec water supply expansion works for Bucaramanga, a city located in northeastern Colombia, with a population of 800,000.

Scope of Services:

  • Demand Studies
  • Supply Sources
  • Master Plans
  • Regulation and Storage Reservoirs
  • Intake Structures and Low-level Outlets
  • Sand and Gravel Traps
  • Conveyance Structures: Channels, Pipes and Tunnels
  • Water Treatment Plants
  • Pumping Stations
  • Water Distribution Networks
  • Wastewater Treatment Plants
  • Sewage and Storm Sewers
  • Environmental and Economical Assessment

Chingaza

The Chingaza System is the most attractive fresh water source for the City of Bogota’s water... more

Chingaza (Expansion)

The Chingaza project is the main water supply source for the City of Bogotá. It is located 55 km
more

San Rafael

San Rafael Project´s objective is to ensure adequate water supply to the City of Bogotá D.C.
more
Tibitoc

The Tibitoc Plant concession contract, in force from 1998 to 2018, establishes that a...
more
Aguablanca

The enlargement works at the plant increased the yield of potable water from 3,3 m³/s to 4,95 m³/s.
more
Misicuni

The objective of the Misicuni Multipurpose Project is to divert the waters of the Misicuni... more
Cali

Among the evaluation of the water use schemes carried out by institutions such as... more

Barranquilla

The project has two main components: water and wastewater, plus a third aspect: institutional... more

Hydropower Projects

Transmission Lines and
Substations

Thermal Power Plants
Water and Wastewater Systems
Industrial Development
Roads and Highways
Transportation
Telecommunications
Oil Industry
Mining
Land Reclamation
Rural Development
Environmental Studies 
Claims, Disputes and Arbitrations


Home  |  Company  |  Service  |  Experience  |  Brochures  |  Site Map  |  Spanish   |   Contact



Copyright© 2004, Ingetec S.A. All rights reserved.
www.ingetec.com.co